S30049 A38 Derby Junction Designing Validation Works

National Highways Limited · awarded 27 January 2026

£452k Award value £452,132
1 Supplier Recorded as a large business
31 May 2026 Runs until from 27 Jan 2026

Who

BuyerNational Highways Limited Birmingham
Supplier Arcadis Consulting UK Limited
Categoryservices
ClassificationDevelopment consultancy services CPV 73220000
Notice published29 January 2026

What it is for

Following on from Phase 1 GAP analysis a Detailed assessment of the design maturity to verify that the 3D digital model accurately represents the intended design, highlight and Risk, or gaps to filled before tender or by the oncoming Delivery Partner. Proposed scope detail to Include: - TA Design maturity assessment (design gap analysis) - completion based on information available to date. - PDP DCO and Stage 5 design basis - define what standards etc. - PDP design composition (List down PDP design deliverables used for this assessment) - PDP gap analysis exercise: a. Stage 5 design package completion status (% age complete, what is remaining) b. Stage 5 design package approval status and if approved with comments their significance (minor / major) (i.e. AIP approved, significance of any comments) - Define and list down design changes required post PDP work (i.e. DCO Requirements work partially completed or was not considered) - Define design changes made post PDP work (i.e. Update of Arcadis work from Nov 2024 to date) - Design opportunities / VE identification - Design risks emerging from prior to current scope including risks highlighted through gap analysis exercise Schedule of regular review meeting to monitor progress between National Highways and Arcadis to ensure output is met - Final deliverable to be in a report format, which should include the following items: - Design overview background (This section to include PDP design prior to their termination of contract) - Design maturity, design completeness, design work remaining, and design status report - Update around assurance completed by Arcadis under TA role - Design opportunities / VE identification/Efficiencies - Carbon and biodiversity position - PDP DCO and Stage 5 design basis - define what standards…

Read the original award notice on Contracts Finder →

Other contracts from this buyer

1634 awards on file, worth £3.4bn.

Everything National Highways Limited has awarded →

Other contracts won by this supplier

10 awards on file, worth £4.4m.

Everything Arcadis Consulting UK Limited has won →