STDC-PROC-0587 - Hinterland Temporary Drainage Channel
TEES VALLEY COMBINED AUTHORITY · awarded 28 October 2025 · delivered in North East
£141k
Award value
£141,098
1
Supplier
Recorded as a large business
31 Dec 2025
Runs until
from 3 Nov 2025
Who
| Buyer | TEES VALLEY COMBINED AUTHORITY Darlington |
|---|---|
| Supplier |
Rainton Construction Limited |
| Category | works |
| Classification | Water installations CPV 39370000 |
| Notice published | 19 May 2026 |
What it is for
Earthworks and related civil engineering operations to construct a temporary drainage channel of approximately 550m in length. Call off under NEPO211 Lot 1:
Read the original award notice on Contracts Finder →
Other contracts from this buyer
200 awards on file, worth £183.4m.
| Awarded | What for | Buyer | Supplier | Value |
|---|---|---|---|---|
| 6 Mar 2023 | Darlington Station Redevelopment (Deed of Variation) - Variation to contractNorth East | TEES VALLEY COMBINED AUTHORITY | WILLMOTT DIXON CONSTRUCTION LIMITED | £36.3m |
| 19 Dec 2024 | STDC-PROC-0476 - Park & Ride Phase 3 (Car Park Construction)North East | TEES VALLEY COMBINED AUTHORITY | Rainton Construction | £11.8m |
| 15 Dec 2022 | South Bank Link RoadNorth East | TEES VALLEY COMBINED AUTHORITY | Rainton Construction Limited | £10.0m |
| 21 Jan 2025 | STDC-PROC-0427North East | TEES VALLEY COMBINED AUTHORITY | Rainton Construction limited | £9.0m |
| 1 Apr 2025 | TVCA-PROC-0498 Adult Skills Fund and FCFJ 2025-26North East | Tees Valley Combined Authority | Middlesbrough College | £6.4m |
Everything TEES VALLEY COMBINED AUTHORITY has awarded →
Other contracts won by this supplier
11 awards on file, worth £1.0bn.
| Awarded | What for | Buyer | Supplier | Value |
|---|---|---|---|---|
| 20 Feb 2025 | Civil Engineering and Infrastructure Works | THE ASSOCIATION OF NORTH EAST COUNCILS LIMITED | Applebridge Construction Limited +33 | £1.0bn |
| 24 Mar 2025 | STDC-PROC-0540 - NZT Water NetworkEngland | South Tees Development Corportation | Rainton Construction | £12.0m |
| 19 Dec 2024 | STDC-PROC-0476 - Park & Ride Phase 3 (Car Park Construction)North East | TEES VALLEY COMBINED AUTHORITY | Rainton Construction | £11.8m |
| 15 Dec 2022 | South Bank Link RoadNorth East | TEES VALLEY COMBINED AUTHORITY | Rainton Construction Limited | £10.0m |
| 21 Jan 2025 | STDC-PROC-0427North East | TEES VALLEY COMBINED AUTHORITY | Rainton Construction limited | £9.0m |